Jeypore, 9th Sept 2025: The doubling of the Koraput–Rayagada Singapore Road railway line has progressed further. Six tunnels will be constructed between Tikiri and Rauli stations as part of this project. A tender worth over Rs 383 crore has been invited for this purpose. The work includes tunnel construction, illumination, and other related works, according to information provided by East Coast Railway.
An e-tender has been floated by the Construction Division of East Coast Railway on behalf of the President of India. The bidding type is EPC (Engineering, Procurement, and Construction) – Single Mode.
Tunnel Construction between Tikiri and Rauli
According to official sources, tunnels numbered 5, 6, 7, 8, 9, 10, 11, and 12 will be constructed as part of the doubling project of the Koraput–Singapore Road railway line. These are located between Tikiri (83.065 km) and Rauli (95.250 km) stations. Besides tunnels, other works like illumination and associated infrastructure will also be carried out.
The total tender value is Rs 383 crore 35 lakh 77 thousand 868.
Two pre-bid conferences have been scheduled on September 10 and September 26.
The bidding will start on October 17 and will close at 12 noon on October 31.
Manual submissions will not be accepted.
The target is to complete construction within 30 months (2.5 years).
About the Project
The Koraput–Singapore Road doubling project spans approximately 165 km. This route, surrounded by hills and mountains, connects Rayagada Junction with Koraput, Jeypore, and Jagdalpur. It also includes large-scale industrial points like Bamanijodi NALCO and Sunabeda HAL.
At Koraput Junction, this line links with the Kotavalasa–Kirandul (KK) line. Although primarily meant for freight transport, this route also accommodates many passenger trains. However, due to being a single-line track and prone to landslides, train operations are frequently affected. The addition of a second line is expected to resolve many of these issues significantly.